Question: Problem 9-23 Cost-Cutting Proposals (LO 2] CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for
Problem 9-23 Cost-Cutting Proposals (LO 2] CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $409,000 is estimated to result in $151,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table) and it will have a salvage value at the end of the project of $52,000. The press also requires an initial investment in spare parts inventory of $15,700, along with an additional $2,700 in inventory for each succeeding year of the project. The shop's tax rate is 22 percent and its discount rate is 9 percent. Calculate the project's NPV. (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) Net present value