Question: Problem A - 3 ( Algo ) A manufacturing firm has discontinued production of a certain unprofitable product line. Considerable excess production capacity was created

Problem A-3(Algo)
A manufacturing firm has discontinued production of a certain unprofitable product line. Considerable excess production capacity was created as a result. Management is considering devoting this excess capacity to one or more of three products: X1, X2, and X3.
Machine hours required per unit are
PRODUCT
MACHINE TYPEX1X2X3Milling machine678Lathe460Grinder1004
The available time in machine hours per week is
MACHINE HOURS PER WEEKMilling machines798Lathes650Grinders122
The salespeople estimate they can sell all the units ofX1andX2that can be made. But the sales potential ofX3is 100 units per week maximum.
Unit profits for the three products are
UNIT PROFITSX1$30X221X319
a.Set up the equations that can be solved to maximize the profit per week.(Leave no cells blank - be certain to enter "0" wherever required.) Problem A-3(Algo)
A manufacturing firm has discontinued production of a certain unprofitable product line. Considerable excess production capacity was created as a result. Management is considering devoting this excess capacity to one or more of three products: X1, X2, and X3.
Machine hours required per unit are
PRODUCT
MACHINE TYPEX1X2X3Milling machine678Lathe460Grinder1004
The available time in machine hours per week is
MACHINE HOURS PER WEEKMilling machines798Lathes650Grinders122
The salespeople estimate they can sell all the units ofX1andX2that can be made. But the sales potential ofX3is 100 units per week maximum.
Unit profits for the three products are
UNIT PROFITSX1$30X221X319
a.Set up the equations that can be solved to maximize the profit per week.(Leave no cells blank - be certain to enter "0" wherever required.) Problem A-3(Algo)
A manufacturing firm has discontinued production of a certain unprofitable product line. Considerable excess production capacity was created as a result. Management is considering devoting this excess capacity to one or more of three products: X1, X2, and X3.
Machine hours required per unit are
PRODUCT
MACHINE TYPEX1X2X3Milling machine678Lathe460Grinder1004
The available time in machine hours per week is
MACHINE HOURS PER WEEKMilling machines798Lathes650Grinders122
The salespeople estimate they can sell all the units ofX1andX2that can be made. But the sales potential ofX3is 100 units per week maximum.
Unit profits for the three products are
UNIT PROFITSX1$30X221X319
a.Set up the equations that can be solved to maximize the profit per week.(Leave no cells blank - be certain to enter "0" wherever required.) Maximize Z =-----X1+------X2+-----X3
s.t MillingX1+X2+ X3<=LathesX1+X2+X3<=GrindersX1+X2+X3<=SalesX1+X2+X3<= X1, X2, X3>=0
b.Solve these equations using the Excel Solver.(Leave no cells blank - be certain to enter "0" wherever required. Round your answers to the nearest whole number. Use your ROUNDED decision variable values to compute total profit.) Decision for X1Decision for X2Decision for X3Total profit
c.How much of each constraint or resource is unused?(Leave no cells blank - be certain to enter "0" wherever required. Round your answers to the nearest whole number. Use your ROUNDED decision variable values to compute the unused resources.) Resources UsedMillingLathesGrindersSales
d-2.WillX3be at maximum sales capacity?
multiple choice
No
Yes
e.Suppose that an additional 150 hours per week can be obtained from the Milling machine by working overtime. The incremental cost would be $5.00 per hour. What is the shadow price for one additional hour of overtime in the Milling machine Department? If this same shadow price must be maintained and if working overtime must remain profitable, should all additional 150 overtime hours be utilized?(Round "shadow price" to 2 decimal places.) The shadow price isper hour. It isto utilize all150additional overtime hours if the optimal solution must be maintained.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!