Question: Problem: A is made from 2 Bs and 1 C B is made from 1 C and 2 Ds Master Schedule calls for 5 0
Problem:
A is made from Bs and C
B is made from C and Ds
Master Schedule calls for A due in week
Part A: Lead time week; On hand inventory ; Lot Size
Part B: Lead time week; On hand inventory ; Lot Size
Part C: Lead time week; On hand inventory ; Lot Size
Part D: Lead time week; On hand inventory ; Lot Size
Chapter MRP Problem Question : In what week should a planned order be released for part A
Chapter MRP Problem Question : What is the planned order quantity for part B
Chapter MRP Problem Question : What is the planned order quantity for Part D
Chapter MRP Problem Question : What is the last planned order quantity for part C
Chapter MRP Problem Question : In what week should a planned order be released for part D
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock