Question: Problem: An Assembly consists of the following elements as given in the table below. Task A B C D E F G H I J

Problem: An Assembly consists of the following elements as given in the table below.
Task A B C D E F G H I J K L
Immediate Predecessor Nil A B B B B C,D G E I,F H,J K
Task Time 12662212751467
The production rate required is one assembly every 15 minute. Determine the minimum no of workstations required so as to minimize the Balance- Delay. Find Balance Delay Station-wise.