Question: Problem - Based Learning Problem - Based Learning ( PBL ) is an important tool that encourages deep learning by discovery. MS Project 2 0
ProblemBased Learning
ProblemBased Learning PBL is an important tool that encourages deep learning by discovery. MS Project
will be presented via a series of PBLdiscovery exercises.
Microsoft Project Exercise
You are presented with the following problem that involves the development of an MIS System.
ID Task name Duration
weeks
Precedence MIS
Staff
User
Staff
Consultant
Start
MIS System Plan
Documentation
Network Plan
Communications
Test MIS Plan
Test Local Nodes
Test Network
Training
End
Resource Availability Rate $hour
MIS Staff
User Staff
Consultant
Set a planned start date for the first Monday of May
Enter the task data into Microsoft Project including precedencies and resource allocations. Dont
forget to enter zero for milestone durations.
Create the Gantt chart. What is the critical path?
View the network diagram.
Add a cost column. What is the total cost?
For every week the project is in execution $ of overheads are added to the project cost. Add a
hammock task to allocate these overhead costs to the project.
Generate a resource histogram resource graph and investigate any overloads. Explore levelling
options. What effect do these have on the project duration and cost? How would you eliminate
overloads? You dont really have a project plan until you allocate resources!
Observe how the project cost changes when the duration of the project changes. What causes the costs to
change?
Generate appropriate cost reports.
How do you display total project costs?
Step by Step Solution
There are 3 Steps involved in it