Question: Problem: Build Milko Corporation has two contracts in progress, the details of which are as follows: A Corp B Corp In Millions Total Contract Price
Problem: Build Milko Corporation has two contracts in progress, the details of which are as follows:
| A Corp | B Corp | |
| In Millions | ||
| Total Contract Price | 300 | 300 |
| Cost Incurred to Date | 90 | 150 |
| Estimated costs to completion | 135 | 225 |
| Payments invoiced and received | 116 | 116 |
Build Milko Corporation measures satisfaction of performance obligations based on percentage of work certified as complete.
Required: Show extracts from the statement of profit or loss and other comprehensive income and the statement of financial position for each contract, assuming they both are certified as 40% and 36% complete.