Question: Problem description: Given the projected demands for the next six months, prepare an initial aggregate production plan that uses only regular time. Then develop an

Problem description:
Given the projected demands for the next six months, prepare an initial aggregate production plan that uses only regular time. Then develop an alternative aggregate production plan that also shows overtime production is utilised to fulfill backorders.
Regular time is 150 units per month. Overtime is a maximum of 20 units per month. Overtime cost is $30 per unit, backorder cost is $20 per unit, inventory holding cost is $5 per unit, regular time cost of $20 per unit, and beginning inventory is zero. Month Forecast
1180
2170
3140
4150
5130
6120 Requirements:
(a). Prepare an initial plan (4 marks)
(b) Prepare an alternative plan (5 marks)
(c) Which plan is better (a) or (b)? Why? (2 marks)
(d) How many units should be produced using overtime hours in the alternative plan?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!