Question: Problem FEX - 0 2 [ Points: 1 / 4 ] , For the tabulated schedule network presented: ( a ) [ Points 0 .

Problem FEX-02[Points: 1/4], For the tabulated schedule network presented:
(a)[Points 0.5/4] Construct and sketch the Precedence Diagram by hand. Apply forward and backward time-stamp analysis, compute Total Float (procrastination time gap) and Free Float (idle/laze time gap) of each activity; identify the Critical Path. First activity starts in day 0.
(b)[Points 0.5/4] Compute the probability of finishing the job in 34 weeks?
\table[[Description,\table[[Activ-],[ity]],\table[[Pre-],[cedence]],\table[[Dura-],[tion]],\table[[Con-],[nection]],\table[[(Opti-],[mistic],[Time)]],\table[[m(Most],[Likely],[Time)]],\table[[b(Pes-],[simistic],[Time)[days]]]],[Foundation,A,-,8,,6,8,10],[Framing,B,A,10,FS+Id,7,10,12],[Walls,C,B, A,7,SS+2d,5,7,8],[Slabs,D,B,6,SF-2d,3,6,8],[Roof,E,C. B,15,FF+ld,11,15,16]]
Problem FEX - 0 2 [ Points: 1 / 4 ] , For the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!