Question: Problem H3: ( 10 paints, based on Example 2 in Chapter 16 ) Suppose that One Hot Cookie (a real company) is looking to create
Problem H3: ( 10 paints, based on Example 2 in Chapter 16 ) Suppose that One Hot Cookie (a real company) is looking to create a Kanban system for their popular large cookies. They have a Production Lead Time of 3 days, with Daily Demand of 200 units per day. Their safety stock is 1 days' worth of supply. Suppose that they think they are best suited with a 7 Kanban system. How large (what size) do those Kanban containers need to be to support a 7 Kanban system