Question: Problem - ( I want also need diagram ) Identify different paths in the network and the critical path for the network shown in below

Problem-(I want also need diagram)
Identify different paths in the network and the critical path for the network shown in below figure. Also find the project duration by using forward and backward pass and float methods.
\table[[Activity,Duration (in weeks),Depends upon],[A,4,-],[B,2,A],[C,2,A, B, F],[D,2,C, L],[E,6,D, G, H],[F,2,A],[G,2,F],[H,3,G, L],[K,5,A],[L,3,F, K]]