Question: PROBLEM ID: RO& 1 ; 2 ; 3 ; 8 ; 8 ; 6 ; 2 ; 2 ; 2 ; 6 ; 7 ;
PROBLEM ID: RO&;;;;;;;;;;;;;;&
Consider the following project activities and determine the resource peak.
Activity Predecessor Duration days Labourers
A
B A
C A
D A
E A
F BD
G B
All activities are connected through FS relationships with no lead or lag.
What is the original project duration just based on CPM; ignoring resource constraints
The CPM based project duration is
days.
What's the maximum number of labourer units you require for this project according to the original schedule above?
The maximum number of labourer units required for this project is
Next consider this limitation: All activities are performed in the same work area; however, only a maximum of labourer units are allowed in the area. This means the original schedule above will not be feasible.
Resolve the resource overallocation following the Least Slack rule also known as "The Minimum Slack Rule" Activities with the most slack are pushed out first.
Make sure you show your calculation steps and explain your reasoning in the solution file that you submit in the context of this assignment.
Calculate the resulting Early Start dates for the activities and enter them below.
Activity ES
A
B
C
D
E
F
G
What is the new project duration, once the resource overallocation has been resolved?
The new project duration is
days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
