Question: Problem II 0 2 - 0 2 ( Points: 1 . 5 / 4 ) . For the low - rise residential house project presented
Problem IIPoints:
For the lowrise residential house project presented in Problem I
aPoints Construct and sketch the Precedence Diagram Whenever passible, employ the cluster hammock method to simplify the network to the major activities, as described in Slide L Scheduling lpdf posted in DL
Project stars on May
Labar weck. Mondays to Saturdays, M to S: PM; Sundays off no work
Holidays no work: Juncteenth Jua Memorial Day May Independence Duy and Labor Day Sep
bPoints Fill the scheduling table below with the corresponding timesiamps for cach activity
cPoints Identify the Critical Path of the project
dPoints A Assume therc's a dclay in actsvity G of days; recalibratc your Precedence Diagram network and identify the critical path. Tip": Add dnys to the original duration of activity G and recompute. Review Example L for further details.
cPoints Compute the probability of finishing the project in days approximately wecks of months
Tip : Exploit MS Excel capabilitics to speced up the calculation and accuracy of tmo stamps. Critical Path. and PERT analysis.
DEL Sereenshotsphotos of handwritten spreadsheet computations, proyressive logical stepbystep, sequential calculationbycalculation. This includes pnntouts of scheduling table, Precedence Diagram network, iorwardbackward timestamp analysis, identificauon of Critical Path, and probabilistic PERT calculations. Points will be discounted for missing unbacked documentation. Numbers outoftheblue will not be accepted
tabletableActivity arrowetable
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock