Question: Problem P7-4 Make-or-Buy Decision For most construction projects, Bradley Heating and Cooling buys sheet metal and forms the metal into heating/cooling ducts as needed. The

Problem P7-4 Make-or-Buy Decision
For most construction projects, Bradley Heating and Cooling buys sheet metal and forms the metal into heating/cooling ducts as needed. The company estimates the costs of making and installing ductwork for Kerry Park shopping mall to be as follows:
Materials $35,000
Labor to form ductwork 4,000
Labor to install ductwork 10,000
Misc. variable costs 1,500
Fixed costs allocated based on labor hours 3,000
Total costs $53,500
The fixed costs relate to the company's building equipment, and office staff. The company plans on billing the Kerry Park
developer $68,000 for services. Bradley is currently behind schedule on other projects and is paying a late penalty of
$1,200 per day. Walt Bradley, the owner of Bradley Heating and Cooling, is considering ordering prefabricated ductwork for
the Kerry Park job. The prefabricated ductwork will cost $42,000 (including the cost of sheet metal). If Walt
buys the prefabricated ductwork, he'll be able to reassign workers to another project and avoid 5 days of
late fees.
Required:
Should Bradley make the ductwork or buy it prefabricated?
Do not buy Prefabricated Buy Prefabricated Buy Difference
Materials Amount Amount Formula
Title Amount Amount Formula
Title Amount Amount Formula
Title Amount Amount Formula
Title Amount Amount Formula
Title Amount Amount Formula
Total Formula Formula Formula
Narrative answer:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!

Q:

\f