Question: PROBLEM: ( Refer to sketch # 1 ) GIVEN: 1 . Influent Elevation of M . H . A - 1 = 1 3 9

PROBLEM: (Refer to sketch #1)
GIVEN: 1. Influent Elevation of M.H. A-1=139.20'
2. Effluent Elevation of M.H. A-2=146.60'
3. Influent Elevation of M.H. A-2=146.90'
4. Effluent Elevation of M.H. A-3=147.72'
5. Bottom of M.H. diameters =4.00'
6. Standard distance from batterboards to invert is as follows:
M.H.A-1 to A-2=10.00'
M.H.A-2 to A-3=10.00'
7. Hub offset is 8.00' for M.H. A-1 to A-2 and 10.00' for M.H. A-2 to A-3. The length of the batterboards is 10.00'.
PROBLEM: 1. Complete the attached set of surveying notes for sewer line construction staking.
2. a. Draw the plan of the sewer line on engineering paper at a scale of 1''=40.00'.
b. Indicate the manholes, the centerline of the sewer line, the location of the hubs, the batterboards and the stations. Note the hub offsets and the stations at each point.
PROBLEM: ( Refer to sketch # 1 ) GIVEN: 1 .

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!