Question: PROBLEM SITUATION #4 Davidson Hardware stocks an expensive composite-based plaster patching compound, currently classified A which is controlled by continuous review. Demand is variable, with
PROBLEM SITUATION #4 Davidson Hardware stocks an expensive composite-based plaster patching compound, currently classified A which is controlled by continuous review. Demand is variable, with an average of 6 pounds per week and a standard deviation of 2 pounds per week. Lead time is constant at one week. The firms current management of the product calls for a safety stock of one (1) pound.
1. The current reorder point for this product is ______ pounds.
a. 5
b. 7
c. 6
d. 8
e. none of the above
2. The current cycle-service level is ______.
a. 0.5
b. 1.29
c. 0.8413
d. 0.6915
e. none of the above
3. If Davidson wanted to change the safety stock so that the cycle-service level became 90 percent, the new reorder point would be ______.
a. 6
b. 9.3
c. 8.6
d. 8
e. none of the above