Question: Problem solving: show all your work and circle your final answers. [100 marks] 1. The processing times and due dates are given in the below

Problem solving: show all your work and circle
Problem solving: show all your work and circle your final answers. [100 marks] 1. The processing times and due dates are given in the below table. J 1 2. 3 4 5 Pj 1 3 5 7 3 dj 2 4 5 17 14 a. For a single machine scheduling, what sequence will minimize both maximum lateness and the maximum tardiness? [7.5 marks] Using the obtained sequence from part (a), complete the following table. [10 marks] J Pj dj . Lj Tj Ej Completion Status