Question: Problem Specification Consider the following incomplete network diagram and answer the questions that follow: Notes: A working day is Monday, Tuesday, Wednesday, Thursday and Friday
Problem Specification
Consider the following incomplete network diagram and answer the questions that follow:
Notes:
A working day is Monday, Tuesday, Wednesday, Thursday and Friday am pm
Staff works Mondays through Friday.
Project start date is April,
No two holidays can be on the same day.
The last Friday of every month is a social day for the company. No work is done on this day.
If a holiday falls on a Saturday, then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.
The following holidays are observed in a year.
January New Year Day
Second Monday in January, March, May, June, August, October, December is EatAllYou
Can day
April Drivers Day
May National Picnic Day
June Parliament Dbar a y
August National Road Safety Day
December Blame Someone Else Day
aHow long will this project take? What is the completion date?
b List all the distinct paths in the project along with their durations.
c Identify all Activities in the above project that have a slack and the amount of slack.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock