Question: Problem Specification Consider the following incomplete network diagram and answer the questions that follow: Notes: A working day is Monday, Tuesday, Wednesday, Thursday and Friday

Problem Specification
Consider the following incomplete network diagram and answer the questions that follow:
Notes:
A working day is Monday, Tuesday, Wednesday, Thursday and Friday (8am -8 pm).
Staff works Mondays through Friday.
Project start date is 1st April, 2024.
No two holidays can be on the same day.
The last Friday of every month is a social day for the company. No work is done on this day.
If a holiday falls on a Saturday, then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.
The following holidays are observed in a year.
January 1- New Year Day
Second Monday in January, March, May, June, August, October, December is Eat-All-You-
Can day
April 10- Drivers Day
May 12- National Picnic Day
June 18- Parliament D\bar (a) y
August 15- National Road Safety Day
December 20th- Blame Someone Else Day
a)How long will this project take? What is the completion date?
b) List all the distinct paths in the project along with their durations.
c) Identify all Activities in the above project that have a slack and the amount of slack.
 Problem Specification Consider the following incomplete network diagram and answer the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!