Problem Specification Consider the following network schedule: Table 1: Network Schedule of an Accounts Payable System...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Problem Specification Consider the following network schedule: Table 1: Network Schedule of an Accounts Payable System Activity 1 Planning meetings 2 Team assignments 3 Gather requirements 4 Analyze existing processes Identify key features 5 6 Develop functional specifications 7 8 9 10 11 12 13 14 15 16 17 18 19 Question 1: Scheduling Techniques 20 21 Design data model and database schema Design user interface Prototype Develop accounts payable application Develop accounts payable reports Perform system testing Fix defects and issues Conduct user acceptance testing Develop user documentation and training Conduct user training Develop data backup and recovery plan Develop disaster recovery plan Conduct system security assessment Implement system security controls Deploy accounts payable system Predecessor(s) - 1 3 2 2, 3, 4 5 5SS 1, 6SS 6,7 8SS 8,9 10SS 11SS 5, 7SS, 9SS, 11, 12 12, 13 6 8, 15 6 17 12, 13, 16, 18 Duration (weeks) 2 1 3 2 2 4 3 3 4 10 4 6 2 4 3 2 2 2 2 2 1 22 Conduct final test 23 Deploy improvements 24 Handover SS-Start to start lag Notes: A working day is Monday, Tuesday, Wednesday, Thursday and Friday (8am - 5pm). Staff works Mondays through Friday. 19SS, 21 21SS,22 22SS, 23 Project start date is 3rd April, 2023. The last Friday of every month is a sports day for the company. No work is done on this day. The following holidays are observed in a year. O 2 1 1 o January 1- New Years Day Second Monday in January, April, May, July, August, October, December is Eat-All-You- Can day April 10-Flower Day May 24 - Mighty Mums Day O June 18 - Love Your Neighbor Day August 17 - Super Dads Day o o December 20th - Blame Someone Else Day If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off. No two holidays can be on the same day. Given the information provided in Table 1 and key notes, answer the following questions. Read the questions carefully, and refer to the notes and table for more information. Required: a) You are tasked to draw using appropriate software (i.e. not using any project management software) an AOA PERT chart for the above project; assuming a finish-start (FS) relationship between activities. (The length of the arrows must be indicative of the duration where possible). (10 marks) b) Draw an AON Chart (also known as Project Network Diagram) clearly stating the ES, EF, LS, and LF for each of the activities for the above project. Use the node style given in lectures for your AON diagram. (10 marks) c) How long will the project take? What is the completion date? (2 marks) d) List all the distinct paths in the project along with their durations. (3 marks) e) Which tasks are on the critical path in the above project? (2 marks) f) Identify all Activities in the above project that have a slack and the amount of slack. (4 marks) g) You have discovered that the competing accounting package (with significant improvements) is scheduled for delivery 2 weeks earlier than your system. Based on your original schedule above, what actions would you take to improve the time to market? (2 marks) h) Pooja is in-charge of activity 15. If activity 15 is delayed by 2 weeks what will be the new project duration and mention the effect? If there is no effect, state 'No change in duration'. (3 marks) i) Create a Gantt chart for the above network schedule using appropriate software learnt in class, indicate appropriate milestones and resources. (6 marks) Problem Specification Consider the following network schedule: Table 1: Network Schedule of an Accounts Payable System Activity 1 Planning meetings 2 Team assignments 3 Gather requirements 4 Analyze existing processes Identify key features 5 6 Develop functional specifications 7 8 9 10 11 12 13 14 15 16 17 18 19 Question 1: Scheduling Techniques 20 21 Design data model and database schema Design user interface Prototype Develop accounts payable application Develop accounts payable reports Perform system testing Fix defects and issues Conduct user acceptance testing Develop user documentation and training Conduct user training Develop data backup and recovery plan Develop disaster recovery plan Conduct system security assessment Implement system security controls Deploy accounts payable system Predecessor(s) - 1 3 2 2, 3, 4 5 5SS 1, 6SS 6,7 8SS 8,9 10SS 11SS 5, 7SS, 9SS, 11, 12 12, 13 6 8, 15 6 17 12, 13, 16, 18 Duration (weeks) 2 1 3 2 2 4 3 3 4 10 4 6 2 4 3 2 2 2 2 2 1 22 Conduct final test 23 Deploy improvements 24 Handover SS-Start to start lag Notes: A working day is Monday, Tuesday, Wednesday, Thursday and Friday (8am - 5pm). Staff works Mondays through Friday. 19SS, 21 21SS,22 22SS, 23 Project start date is 3rd April, 2023. The last Friday of every month is a sports day for the company. No work is done on this day. The following holidays are observed in a year. O 2 1 1 o January 1- New Years Day Second Monday in January, April, May, July, August, October, December is Eat-All-You- Can day April 10-Flower Day May 24 - Mighty Mums Day O June 18 - Love Your Neighbor Day August 17 - Super Dads Day o o December 20th - Blame Someone Else Day If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off. No two holidays can be on the same day. Given the information provided in Table 1 and key notes, answer the following questions. Read the questions carefully, and refer to the notes and table for more information. Required: a) You are tasked to draw using appropriate software (i.e. not using any project management software) an AOA PERT chart for the above project; assuming a finish-start (FS) relationship between activities. (The length of the arrows must be indicative of the duration where possible). (10 marks) b) Draw an AON Chart (also known as Project Network Diagram) clearly stating the ES, EF, LS, and LF for each of the activities for the above project. Use the node style given in lectures for your AON diagram. (10 marks) c) How long will the project take? What is the completion date? (2 marks) d) List all the distinct paths in the project along with their durations. (3 marks) e) Which tasks are on the critical path in the above project? (2 marks) f) Identify all Activities in the above project that have a slack and the amount of slack. (4 marks) g) You have discovered that the competing accounting package (with significant improvements) is scheduled for delivery 2 weeks earlier than your system. Based on your original schedule above, what actions would you take to improve the time to market? (2 marks) h) Pooja is in-charge of activity 15. If activity 15 is delayed by 2 weeks what will be the new project duration and mention the effect? If there is no effect, state 'No change in duration'. (3 marks) i) Create a Gantt chart for the above network schedule using appropriate software learnt in class, indicate appropriate milestones and resources. (6 marks)
Expert Answer:
Related Book For
Project management the managerial process
ISBN: 978-0073403342
5th edition
Authors: Eric W Larson, Clifford F. Gray
Posted Date:
Students also viewed these general management questions
-
Three transactions for Sunland Gifts are presented here. On October 2, Sunland Gifts purchased $35,500 of merchandise from Sea Toys, terms 1/10, n/30. On October 6, Sunland Gifts returned $2,800 of...
-
Determine the transfer function from U(s) to Y(s) for the following block diagram. Provided are some recommended steps to take: a. Label each signal (line with arrow) b. Write the equation for each...
-
Have you ever had to cope with the loss of a loved one? If so, what concepts described in this section provide context that may help you understand your experience and process of grieving?
-
Why is participation good for the planning process?
-
Alberta Limited needs a cash budget for the month of November. The following information is available: a. The cash balance on November 1 is $6,000. b. Sales for October and November are $80,000 and...
-
What is the function of an administrative agency?
-
All of us come into contact with distributed systems almost every day, even if it is only while shopping at Walmart or Sears. Describe a distributed system with which you have come in contact. In...
-
Headland Hardware's payroll for November is summarized below. Amount Subject to Payroll Taxes Unemployment Tax Payroll Wages Due FICA Federal State Factory $124,000 $124,000 $39,000 $39,000 Sales...
-
In 2000 or more words Discuss all ethical issues/questions related to the topic Gangs in America and the strategies used to address the problem in the United States. Hint* 1. Include what are the...
-
Danielle is a contractor and operates her own home remodeling business. She just completed two projects, revealed the finished products to her clients, and submitted the invoices to them. At this...
-
What are the key challenges in designing fault-tolerant operating systems capable of providing seamless continuity of service in the face of hardware failures, software errors, and malicious attacks,...
-
Let f(x) = x+7x+12 and g(x) = x-9. A. Find (f*g)(x). B. Find (4)(x).
-
You are a paid intern at Bearkat Marketing, where you have worked for two years designing promotional materials for local events. You often end up working after hours on weekends to ensure your...
-
Elaborate on the role of microkernel architectures in modern operating systems, highlighting their advantages and challenges in terms of modularity, extensibility, and fault isolation, and...
-
AIco, a private company (not a public company), made a two-year employment contract to attract Yoshi as its Chief Compliance Officer. Each year under the contract, Aico will pay Yoshi $200,000 cash...
-
A bubble-point liquid feed is to be distilled as shown in Figure. Use the Edmister group method to estimate the mole-fraction compositions of the distillate and bottoms. Assume initial overhead and...
-
What are the unique challenges to managing a virtual project team?
-
1. How effective has Tran been as a project manager? Explain. 2. What problem(s) does Tran face? 3. How would you go about solving them? Why? Tran was taking his dog Callie on her evening walk as the...
-
How would a project manager use the CPI?
-
One might naively think that a collection \(\left(X_{t}, t \in \mathbb{R}^{+} ight)\)of independent r.v's may be chosen "measurably," i.e., with the map \[\left(\mathbb{R}^{+} \times \Omega,...
-
Chi-squared Law. A noncentral chi-squared law \(\chi^{2}(\delta, \alpha)\) with \(\delta\) degrees of freedom and noncentrality parameter \(\alpha\) has the density \[\begin{aligned}f(x ; \delta,...
-
If \(X\) is a positive random variable, prove that its negative moments are given by, for \(r>0\) : (a) \(\quad \mathbb{E}\left(X^{-r} ight)=\frac{1}{\Gamma(r)} \int_{0}^{\infty} t^{r-1}...
Study smarter with the SolutionInn App