Question: Problem Statement: A dairy processing plant receives 1 8 tons of milk at 6 C every day at 0 5 : 0 0 AM .

Problem Statement:
A dairy processing plant receives 18 tons of milk at 6C every day at 05:00 AM.
14 tons of this milk is used for the production of pasteurized milk (HTST), and
the remaining part is used for the production of ayran.
Pasteurized milk must be ready for distribution at 07:00 AM, and ayran must
be ready at 11:00 AM. Ayran is prepared by mixing pasteurized milk with an
equal amount of water at 20C. Therefore, the temperature must be 45C
when the contents are mixed in the pasteurizer; culture is added at this
temperature. The contents of the fermentation tank are kept at 45C for 3.5
hours. Pasteurized milk and ayran are delivered to the filling areas at 4C.
Assume that the filling time for pasteurized milk and ayran is approximately 30
minutes.
Tasks:
a) Prepare a block diagram for this dairy processing plant and calculate the
mass and energy balances.
b) Calculate the capacity of the tanks, other necessary equipment, and the
size of all pumps.
c) Calculate the required number of plates for the plate heat exchangers used
in pasteurization and ayran production.
 Problem Statement: A dairy processing plant receives 18 tons of milk

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Chemical Engineering Questions!