Question: Problem Statement: Critical Path Method The junior assistant of project manager was assigned to prepare a PERT chart from the information given below. He has
Problem Statement: Critical Path Method
The junior assistant of project manager was assigned to prepare a PERT chart from the information given below. He has done with the assignment and asked you to review the same. After carefully checking, you have noticed that there are some mistakes in the chart.
| Activity | Predecessor | Duration (days) |
| A | - | 3 |
| B | A | 4 |
| C | A | 2 |
| D | A | 5 |
| E | C,B | 1 |
| F | C,E | 2 |
| G | C,D,F | 4 |
| H | F,G | 3 |
| I | G | 4 |
| J | H,I | 5 |
| K | J | 3 |

Required:
- You are required to highlight the mistakes by either mentioning on the chart or by written it down.
- Draw the corrected PERT chart.
- Mention the activities which are on the CP.
- Calculate the total duration of this project by performing forward and backward passes.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
