Question: Problem Statement: You are hired as a project manager for a software development company launching a new mobile application. Your task is to plan, schedule,

Problem Statement:
You are hired as a project manager for a software development company launching a new mobile application. Your task is to plan, schedule, and optimize the project timeline while ensuring the project goals are met.
Part 1: CPM (Critical Path Method)
The project involves the following activities:
1. Construct the project network diagram and identify the critical path.
2. Calculate the project completion time and total float for each activity.
3. Which activities need to be monitored closely to avoid project delays?
Part 2: PERT (Program Evaluation and Review Technique)
Given the uncertainties in development, the duration of each task may vary. Use the three-time estimate (Optimistic, Most Likely, Pessimistic) for the Backend development (Activity C):
- Optimistic (O): 4 days
- Most Likely (M): 6 days
- Pessimistic (P): 10 days
1. Calculate the expected time and variance for Activity C.
2. Find the probability that the project will be completed within \(\mathbf{18}\) days.
Part 3: Goal Programming
The project must meet multiple objectives:
- Goal 1: Complete the project within 20 days.
- Goal 2: Keep the cost below \$50,000.
- Goal 3: Achieve a user satisfaction score of \(90\%\).
However, there are trade-offs between these goals (e.g., reducing time increases cost). Formulate this as a goal programming problem and describe how you would balance these competing objectives.
 Problem Statement: You are hired as a project manager for a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!