Question: Problem Statement: You are hired as a project manager for a software development company launching a new mobile application. Your task is to plan, schedule,
Problem Statement:
You are hired as a project manager for a software development company launching a new mobile application. Your task is to plan, schedule, and optimize the project timeline while ensuring the project goals are met.
Part : CPM Critical Path Method
The project involves the following activities:
Construct the project network diagram and identify the critical path.
Calculate the project completion time and total float for each activity.
Which activities need to be monitored closely to avoid project delays?
Part : PERT Program Evaluation and Review Technique
Given the uncertainties in development, the duration of each task may vary. Use the threetime estimate Optimistic Most Likely, Pessimistic for the Backend development Activity C:
Optimistic O: days
Most Likely M: days
Pessimistic P: days
Calculate the expected time and variance for Activity C
Find the probability that the project will be completed within mathbf days.
Part : Goal Programming
The project must meet multiple objectives:
Goal : Complete the project within days.
Goal : Keep the cost below $
Goal : Achieve a user satisfaction score of
However, there are tradeoffs between these goals eg reducing time increases cost Formulate this as a goal programming problem and describe how you would balance these competing objectives.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
