Question: PROBLEMS 1. Using the BOM shown below, how many of part E will be needed if 20 units of end item A are needed? How

PROBLEMS 1. Using the BOM shown below, how many of part E will be needed if 20 units of end item A are needed? How Page 506 many of part C will be needed? A 1 week B (2) C (1) 2 weeks D (2) 1 week 3 weeks E (4) F (2) C(1) 2 weeks 3 weeks E (2) 1 week 2 weeks Show Transcribed Text 1. Using the BOM shown below, how many of part E will be needed it 20 units of end item A are needed? How many of part C will be needed? A 1 week B (2) C (1) D (2) 2 weeks 1 week 3 weeks E (4) F (2) C (1) E (2) 2 weeks 3 weeks 1 week 2 weeks 2. Based on the BOM in problem 1, what is the cumulative lead time for end item A? How will this information used