Question: Problems for Section 3 . 4 : Layout Decision Models 1 . Burns Boats wants to assemble 5 0 boats per 8 - hour day,
Problems for Section : Layout Decision Models Burns Boats wants to assemble boats per hour day, using a production line. Total task time for each boat is minutes. a What is the takt time? What is the theoretical minimum number of workstations needed? b Suppose the longest individual task takes minutes. Will Burns be able to accomplish its goal? Justify your answer.