Question: Proceed to solve the following problem by Critical Path Method. Name of Activity Immediate Predecessors Activity Time in Days A None 5 B None 7
Proceed to solve the following problem by Critical Path Method.
| Name of Activity | Immediate Predecessors | Activity Time in Days |
| A | None | 5 |
| B | None | 7 |
| C | A | 2 |
| D | A | 6 |
| E | A | 10 |
| F | E | 4 |
| G | D,F | 10 |
| H | B,C | 8 |
| I | G,H | 2 |
Find out the following:
- Sketch the whole network.
- Find out critical path by analyzing and showing ES, EF, LS, LF and float in a table.
- Find out the project completion time. This question in totally unique. Please answer it correctly. Very important for me. Thanks a lot.