Question: Process A has fixed costs of $1000 and variable costs of $5 per unit. Process B has fixed costs of $500 and variable costs of
Process A has fixed costs of $1000 and variable costs of $5 per unit. Process B has fixed costs of $500 and variable costs of $15 per unit. Process C has fixed costs of $200 and variable costs of $19. What is the crossover point between process A and process C? OA. 57.1 units O B. $9,500 O C. 50 units OD. 60 units O E. $5,000 2
Process A has fixed costs of $1000 and variable costs of $5 per unit. Process B has fixed costs of $500 and variable costs of $15 per unit. Process C has fixed costs of $200 and variable costs of $19. What is the crossover point between process A and process C ? A. 57.1 units B. $9,500 C. 50 units D. 60 units E. $5,000