Question: Process A has total fixed costs of $9,600 and variable cost per-unit of $10. Process B has total fixed costs of $15,000 and variable cost

 Process A has total fixed costs of $9,600 and variable cost

Process A has total fixed costs of $9,600 and variable cost per-unit of $10. Process B has total fixed costs of $15,000 and variable cost per-unit of $7. Above what quantity does Process B become the most cost-effective alternative? 1,0001,9001,8001,200