Question: Process Analysis with multiple flow units Consider a process consisting of 5 resources that are operated 8 hours per day. The process works on 3
Process Analysis with multiple flow units
Consider a process consisting of resources that are operated hours per day.
The process works on different products A B and C:
Demand for the different products is as follows: unitsd product A;
unitsd product B; unitsd product C
Questions
What is the bottleneck?
What is the flow rate for each flow unit assuming that demand must be
served in the mix described above?
Resource No of
workers
Processing Time
for A minunit
Processing Time
for B minunit
Processing Time
for C minunit