Question: Process Arrival Burst P1 3 10 P2 6 4 Priority 8 2 P3 8 8 P4 9 2 P5 11 9 For the pre-emptive versions
Process Arrival Burst P1 3 10 P2 6 4 Priority 8 2 P3 8 8 P4 9 2 P5 11 9 For the pre-emptive versions of each of the following schedulers: FCFS SJF Priority Round Robin Create the following: A Gantt chart showing when the processes arrive and complete. You cannot schedule a pro that has not arrived. A table showing, for each process: o The process ID The arrival time The completion time (tick at which the process completes) o The turnaround time (elapsed time from arrival to completion)