Question: Process Chas five activities in a straight line. The cycle time for Activity 1 is 10 seconds, Activity2 is 35 seconds, Activity3 is 30 seconds,

Process Chas five activities in a straight line. The cycle time for Activity 1 is 10 seconds, Activity2 is 35 seconds, Activity3 is 30 seconds, Activity 4 is 80 seconds, and Activity is 40 seconds. The rush hour flow time is 1.5 POINTS for this question O a. 40 seconds O b. None of the options are correct Oc. 10 seconds O d. 30 seconds O e. 195 seconds