Question: PROCESS FLOW --- Check ID and boarding pass (45 seconds) - Prepare for check (4 minutes) - Place item on the conveyor (1 minute) -
PROCESS FLOW --- Check ID and boarding pass (45 seconds) - Prepare for check (4 minutes) - Place item on the conveyor (1 minute) - Pass through metal detector (30 seconds) - Collect items (2 minutes)
- Given the process flow for airport screening, calculate the following:
- Activity Times for each Activity
- Unit Capacities for each Activity
- Bottleneck (name the Activity)
- Process Capacity
- Throughput rate
- Throughput Rate