Question: Process p is currently running when process q arrives at the Ready List. The Operating System waits until p is done processing before scheduling q

Process p is currently running when process q arrives at the Ready List. The Operating System waits until p is done processing before scheduling q. This is an example of _____________________.
Group of answer choices
non-preemptive scheduling
preemptive scheduling
just-in-time scheduling
delayed scheduling