Question: Consider the following table: Process PO P1 P2 P3 Burst 6 Ops: A. 014 B. 16 Arrival time 0.0 F C. 10 0.5 1.0
Consider the following table: Process PO P1 P2 P3 Burst 6 Ops: A. 014 B. 16 Arrival time 0.0 F C. 10 0.5 1.0 2 Priority 8 1.5 1 Calculate Total Waiting Time' for P1 when Priority Algorithm is used? 4