Question: Process Selection and Layout The assembly station was designed to process the 12 activities required to make the part through some workstations. The following table

Process Selection and Layout The assembly station was designed to process the 12 activities required to make the part through some workstations. The following table shows the activities, their processing time, and their precedence requirements. *Graph the precedence diagram and assign tasks to work-stations so that the assembly line can produce 221units per (7hour-day).

* What is the cycle time?

Task Immediate predecessor Task Time
a - 0.5
b a 1.4
c a 1.2
d a 0.7
e b . c 0.5
f d 1.0
g e 0.4
h g 0.3
i f 0.5
j e , i 0.8
k h , j 0.9
m k 0.3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!