Question: Processes A, B, C, D, E, and F require service times of 3, 5, 2, 5, 3, and 5. Their arrival times are 0,

Processes A, B, C, D, E, and F require service times of

Processes A, B, C, D, E, and F require service times of 3, 5, 2, 5, 3, and 5. Their arrival times are 0, 1, 3, 9, 10, and 12. What is the average turnaround time, waiting time, response time, and throughput when using SRJF, RR (q=2), and MLF (q=22+1). Show your work.