Question: Processing time for eight projects, displayed in the sequence they arrived. Project P1 P2 P3 P4 P5 P6 P7 P8 Processing time (hours) 5 1

Processing time for eight projects, displayed in the sequence they arrived.

Project P1 P2 P3 P4 P5 P6 P7 P8
Processing time (hours) 5 1 1 3 7 5 2 1.75

2. Given the projects displayed in table above, if FCFS is used to sequence the jobs, what is the average flow rate of the projects?

Note: Round your answer to 2 decimal places.

3. Given the projects displayed in table above, if FCFS is used to sequence the jobs, what is the average flow time of the projects?

Note: Round your answer to 1 decimal place.

4. Given the projects displayed in table above, if FCFS is used to sequence the jobs, what is the average inventory of the projects?

Note: Use your rounded answers from Parts 2 and 3. Round your answer to 1 decimal place.

5. Given the projects displayed in table above, if SPT is used to sequence the jobs, what is the average flow rate of the projects?

Note: Round your answer to 2 decimal places.

6. Given the projects displayed in table above, if SPT is used to sequence the jobs, what is the average flow time of the projects?

Note: Round your answer to 1 decimal place.

7. Given the projects displayed in table above, if SPT is used to sequence the jobs, what is the average inventory of the projects?

Note: Use your rounded answers from Parts 5 and 6. Round your answer to 1 decimal place.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!