Question: Processing time for eight projects, displayed in the sequence they arrived. Project P1 P2 P3 P4 P5 P6 P7 P8 Processing time (hours) 5 1
Processing time for eight projects, displayed in the sequence they arrived.
| Project | P1 | P2 | P3 | P4 | P5 | P6 | P7 | P8 |
|---|---|---|---|---|---|---|---|---|
| Processing time (hours) | 5 | 1 | 1 | 3 | 7 | 5 | 2 | 1.75 |
2. Given the projects displayed in table above, if FCFS is used to sequence the jobs, what is the average flow rate of the projects?
Note: Round your answer to 2 decimal places.
3. Given the projects displayed in table above, if FCFS is used to sequence the jobs, what is the average flow time of the projects?
Note: Round your answer to 1 decimal place.
4. Given the projects displayed in table above, if FCFS is used to sequence the jobs, what is the average inventory of the projects?
Note: Use your rounded answers from Parts 2 and 3. Round your answer to 1 decimal place.
5. Given the projects displayed in table above, if SPT is used to sequence the jobs, what is the average flow rate of the projects?
Note: Round your answer to 2 decimal places.
6. Given the projects displayed in table above, if SPT is used to sequence the jobs, what is the average flow time of the projects?
Note: Round your answer to 1 decimal place.
7. Given the projects displayed in table above, if SPT is used to sequence the jobs, what is the average inventory of the projects?
Note: Use your rounded answers from Parts 5 and 6. Round your answer to 1 decimal place.