Question: Processing time for jobs A, B, C, and D are 2, 10, 5, and 22 days on a machine. Using LPT rule, average completion time
Processing time for jobs A, B, C, and D are 2, 10, 5, and 22 days on a machine. Using LPT rule, average completion time will be: