Question: Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest - due -
Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliestduedate rule.
tableJobABCDEProcessing time weeksDue time weeks
What would be the lateness of job
The lateness for job B
weeks
What would be the tardiness of job
The tardiness for job E
weeks
What is the maximum tardiness for this set of jobs?
Note: Round your answer to decimal place.
The maximum tardiness
weeks
What is the average flow time for this set of jobs?