Question: Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest - due -

Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule.
\table[[Job,A,B,C,D,E],[Processing time (weeks),2,1.1,1,4,0.9],[Due time (weeks),2,6,3,4,5]]
What would be the lateness of job B?
The lateness for job B
weeks
13. What would be the tardiness of job E?
The tardiness for job E
weeks
14. What is the maximum tardiness for this set of jobs?
Note: Round your answer to 1 decimal place.
The maximum tardiness
weeks
15. What is the average flow time for this set of jobs?
 Processing times and due dates for five jobs are shown in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!