Question: Product A B C Price $ 4 5 0 $ 4 0 0 $ 5 0 0 Material Cost $ 5 0 $ 4 0

Product
A
B
C
Price
$450
$400
$500
Material Cost
$50
$40
$110
Weekly Demand
100
75
40
Processing Time Station 1
60
0
30
Processing Time Station 2
10
60
0
Processing Time Station 3
20
30
40
Match the correct scheduling sequence for the bottleneck and the traditional method