Question: Product A is made from three components, B, C, and D. It takes one B, two C, and three D to make a single product
Product A is made from three components, B, C, and D. It takes one B, two C, and three D to make a single product A. Use this information together with the data below to make MRP for A, B, C. and D.
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| MPS (A) |
| 100 | 220 | 80 |
| Part | Lot size | Lead time | On Hand |
| A | 100 | 1 | 50 |
| B | Lot for Lot | 2 | 80 |
| C | 60 | 1 | 20 |
| D | Lot for Lot | 1 | 200 |
Step by Step Solution
There are 3 Steps involved in it
To create a Material Requirements Planning MRP schedule for Product A and its components B C and D we need to follow these steps Step 1 Determine Gros... View full answer