Question: Product costs incurred after the split - off point in a joint processing environment are called: A . non - relevant costs B . joint

Product costs incurred after the split-off point in a joint processing environment are called:
A.
non-relevant costs
B.
joint product costs
C.
scrap costs
D.
Separable processing costs