Question: Product N is distributed through two Distribution Centers. The DRP Planned Order Releases for each DC and the header information for the Factory MPS are

Product N is distributed through two Distribution
Product N is distributed through two Distribution Centers. The DRP Planned Order Releases for each DC and the header information for the Factory MPS are shown below. Which week is the last Master Schedule Release? PRODUCT N Week 1 DC1 Planned Order Release Week 2 Week 3 Week 4 5 2 8 4 DC2 Planned Order Release 6 21 10 3 MPS: PRODUCT N Lead Time 2 weeks Start Inventory| 19 units Lot Size 25 units Reorder 3 units Slide1.JPG o Week 1 O Week 2 Week 3 Week 4