Question: production and operations management please answer Consider the activities, durations, and predecessor relationships in the following network. a) Draw the network. b) Identify the critical
production and operations management
Consider the activities, durations, and predecessor relationships in the following network. a) Draw the network. b) Identify the critical path and completion time of this project. c) What is the activity variance along the critical path? n Activity Predecessor Optimistic Most Likely Pessimistic A 12 16 25 B 7 14 22 5 10 14 D 15 18 25 E 8 12 18 1 B 9 1 15 G F 18 22 29 D, E,G 15 19 27