Question: Production Average: 8 Days St. Dev: 2.6 days Shipping to Port Average: 5 Days St. Dev: 1.2 days Shipping to USA Average: 28 Days St.

 Production Average: 8 Days St. Dev: 2.6 days Shipping to PortAverage: 5 Days St. Dev: 1.2 days Shipping to USA Average: 28

Production Average: 8 Days St. Dev: 2.6 days Shipping to Port Average: 5 Days St. Dev: 1.2 days Shipping to USA Average: 28 Days St. Dev: 6 days Shipping to Distribution Center Average: 2 Days St. Dev: 1.3 days Shipping to Store Average: 3 Days St. Dev: 1.2 days Calculate the overall standard deviation of the process. 2.467.467.2312.36.885.76 Production Average: 8 Days St. Dev: 2.6 days Shipping to Port Average: 5 Days St. Dev: 1.2 days Shipping to USA Average: 28 Days St. Dev: 6 days Shipping to Distribution Center Average: 2 Days St. Dev: 1.3 days Shipping to Store Average: 3 Days St. Dev: 1.2 days What is the probability of fulfilling a custom order in 51 days (rounded to full percentage)? 13%82%12%71%77%85%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!