Production Costs Work in process, beginning of period: Materials$5,200 Labor 4,600 Factory overhead 2,000 $11,800 Costs incurred
Fantastic news! We've Found the answer you've been seeking!
Question:
Production Costs
Work in process, beginning of period:
Materials$5,200
Labor 4,600
Factory overhead 2,000 $11,800
Costs incurred during month:
Materials$20,000
Labor 15,000
Factory overhead 12,000 47,000
Total $58,800
======
Production Report
Finished and transferred to stockroom during month 18,000
Work in process, end of period, 2/3 completed3,000
Required:
Prepare cost of production summary for March.