Question: Production data at the 40th day Activity Predecessor Duration Budget Actual Cost % complete A -- 14 DAYS 12000 14000 100 B -- 21 DAYS
| Production data at the 40th day | |||||
| Activity | Predecessor | Duration | Budget | Actual Cost | % complete |
| A | -- | 14 DAYS | 12000 | 14000 | 100 |
| B | -- | 21 DAYS | 8000 | 7600 | 100 |
| C | A | 14 DAYS | 10000 | 11000 | 100 |
| D | A | 35 DAYS | 24000 | 20000 | 30 |
| E | B,C | 28 DAYS | 16000 | 12000 | 20 |
Calculate the cost, schedule, and time variances. Also calculate the CPI, SPI, CSI, and the ETC and EAC.
Ignoring the actual completion percentages in the table and applying 50-50 percent completion rule for PV and EV, calculate the cost and schedule variances, CPI, SPI, CSI, ETC, and EAC.