Question: Production data at the 40th day Activity Predecessor Duration Budget Actual Cost % complete A -- 14 DAYS 12000 14000 100 B -- 21 DAYS

Production data at the 40th day
Activity Predecessor Duration Budget Actual Cost % complete
A -- 14 DAYS 12000 14000 100
B -- 21 DAYS 8000 7600 100
C A 14 DAYS 10000 11000 100
D A 35 DAYS 24000 20000 30
E B,C 28 DAYS 16000 12000 20

Calculate the cost, schedule, and time variances. Also calculate the CPI, SPI, CSI, and the ETC and EAC.

Ignoring the actual completion percentages in the table and applying 50-50 percent completion rule for PV and EV, calculate the cost and schedule variances, CPI, SPI, CSI, ETC, and EAC.