Question: production planning Question 3: (30 points) (This question can be solved in 15 minutes easily) Find the optimal solution of the following 2 level, flow

production planning
production planning Question 3: (30 points) (This
Question 3: (30 points) (This question can be solved in 15 minutes easily) Find the optimal solution of the following 2 level, flow shop, min Cmax problem. What is the Cmax value in your solution? What is the average waiting time for the optimal solution? Item 1 P1 17 P2 3 2 10 9 3 14 2 4 11 11 5 3 12 6 10 15