ProgramEvaluation and Review Technique ( PERT ). It is aproject management tool used to schedule, organize, andcoordinate
Question:
ProgramEvaluation and Review Technique (PERT). It is aproject management tool used to schedule, organize, andcoordinate tasks within a project. It is basically a methodto analyse the tasks involved in completing a givenproject.
You are the projectmanager in charge of planning and coordinating the setting up of a new plant in the manufacturing sector for your company. Youhave listed a number of key activities needed for thecompletion of the project. Details of the activities are tabulated below:
Activity | Most optimistic time (a) | Most likely time (m) | Most pessimistic time (b) |
(1-2) | 11 | 11.5 | 15 |
(2-3) | 11 | 12 | 13 |
(2-4) | 11 | 13 | 15 |
(3-5) | 13 | 14 | 15 |
(4-5) | 12 | 13 | 14 |
(4-6) | 13 | 15 | 17 |
(5-7) | 14 | 15 | 16 |
(6-7) | 16 | 17 | 18 |
(7-8) | 12 | 14 | 16 |
(7-9) | 15 | 16 | 18 |
(8-10) | 11 | 12 | 13 |
(9-10) | 13 | 15 | 17 |
(i) Construct a PERT network. (17marks)
(ii) State the critical path and thecompletion time.(2 marks)
(iii) Calculate the variance for eachevent. (6 marks)