Question: PROGRAMME: POSTGRADUATE DIPLOMA IN SUPPLY CHAIN MANAGEMENT MODULE: PURCHASING AND SUPPLY CHAIN MANAGEMENT Total Marks: 7 0 QUESTION ONE [ 5 0 ] Read the
PROGRAMME: POSTGRADUATE DIPLOMA IN SUPPLY CHAIN MANAGEMENT
MODULE: PURCHASING AND SUPPLY CHAIN MANAGEMENT
Total Marks:
QUESTION ONE
Read the scenario below and answer the following questions:
Managing Supplier Quality: Integrated Devices
Bill Edwards is a quality engineer assigned to the Injected Molding Commodity Team at
Integrated Devices. The commodity team is responsible for evaluating, selecting, and
negotiating agreements with plasticinjected molding suppliers to be used throughout
Integrated Devices. The team is also responsible for improving service quality and material
that Integrated Devices receives from its suppliers. Bills role after supplier selection involves
working directly with suppliers that require training or technical assistance concerning quality
control and quality improvement.
The company spends about of each sales dollar on purchased goods and services, so
suppliers have a major impact on product quality.
Bill just received a call concerning a recurring manufacturing problem at Integrated Devices
Plant No The plant buyer said the plant is experiencing some quality variability problems
with a key plasticinjected molding component supplied by Trexler Plastics. The component is
sometimes too short or too long to fit properly with other components within the finished
product. On occasion, the bracket snaps, causing endproduct failure. Although the unit cost
of the plasticinjected molding component is only $ these quality issues length variability
and snapping are creating production problems that far exceed the components purchase
price.
The local buyer announced he was having difficulty resolving the problem and asked for
support from the corporate commodity team. The buyer said, You corporate guys selected
this supplier that we all have to use. The least you can do is to help us out of the jam your
supplier choice is causing. The buyers comment surprised Bill, although Bill would soon
come to understand that plant personnel resented not being able to select their own suppliers.
After investigating the problem during a tensionfilled meeting with Plant No personnel, Bill
determined he would have to visit the supplier directly. He would work with Trexlers process
engineers to address the manufacturing variability caused by the nonconforming component.
Bill went back and reviewed his teams actions when selecting a single supplier to provide an
entire family of plasticinjected moldings.
Trexler had quoted the lowest price of all competing suppliers and had provided samples that
passed Integrated Devices engineering tests.
Upon his arrival at the supplier, Bill learned that Trexler did not have a dedicated process
engineer. One engineer, Steve Smith, was responsible for plant layout, process, quality, and
industrial engineering. This individual, who was hired only two months previously, was still
becoming familiar with Trexlers procedures. When Bill asked to review the suppliers quality
control procedures, Steve had to ask several people before he could locate Trexlers
procedures manual.
Bill decided that his first step should be to understand the process responsible for producing
the defective component. At an afternoon meeting, Bill asked Steve for actual output data from
Trexlers process. Steve explained they did not collect data for process capability studies or
for statistical control charting of continuous production. However, he did say that sometimes
things dont seem to be operating well with the equipment that produces the component.
Trexler uses an inspector to examine every finished item to determine if it should be shipped
to the customer.
After explaining the basics of process capability to Steve, Bill asked him to collect data from
the process that produced the bracket component. Bill requested that Steve take exact
measurements periodically from the process so they could draw statistical conclusions. Bill
said he would return in three days to examine the data.
Upon his return three days later, Steve shared with Bill the details of the data collection effort
see Exhibit
Component: # Description: Bracket
Design specification: pm inches
Once Bill calculated a preliminary process capability from this data and examined the training
and quality control procedures at Trexler, he realized he had some serious work ahead of him.
Questions:
Provide an overview of Integrated Device's purchasing function. What is the role of
purchasing in the company's overall operations, and how does it contribute to achieving
business objectives?
Analyse the criteria Integrated Device uses to evaluate and select suppliers. Outline the
key factors that the company should consider when choosing suppliers for its purchasing
needs.
QUESTION TWO
Explore the role of cost reduction as one of the key objectives of purchasing and supply
management. How can o
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock