Question: PROJ - 1 0 0 9 - Project Management Group Case Study 5 Ch . 9 Reducing Project Duration Use the following information to compress

PROJ-1009- Project Management
Group Case Study 5 Ch.9 Reducing Project Duration
Use the following information to compress one time unit per move using the least-cost method. Assume the total indirect cost for the project is $2,000 and there is savings of $100 per time unit reduced. Calculate the total direct, indirect, and project costs for each duration and answer the following.
1. What is the maximum crash time in weeks?
2. Total direct cost at maximum crash time in dollars?
3. What is the optimum crash point in weeks and dollars Direct Cost at 20 weeks = $6000