Question: PROJECT 1 : Suburban Homes Construction ( SHC ) Project. Scope Overview. Building a single - family, partially custom - designed home as required by
PROJECT : Suburban Homes Construction SHC Project.
Scope Overview. Building a singlefamily, partially customdesigned home as required by Mr and Mrs
John Thomas on Strath Drive, Alpharetta, Georgia. The singlefamily home will have the following
features:
ft home with bedrooms and baths
Flooring hardwood on the first floor, tiles in the kitchen and bathrooms, carpet in bedrooms
Granite kitchen countertops, GE appliances in the kitchen
car garage and external landscaping
Ceiling foot on first floor and vaulted foot ceilings in bedrooms
Business case. Suburban Homes is in the business of constructing highquality homes at an affordable
cost with luxury options to provide quality of life for families. The business strategy is to use the best
construction technologies and practices to enhance productivity and increase profits, while offering cost
effective and bestvalue homes for all its customers simultaneously. The current project, Suburban Park
Homes GA is aimed to expand business operations in Georgia.
Milestone Schedule and Deliverables. CM Construction Manager; PM Project Manager
Milestone Completion
Date
Stakeholder
Judge Acceptance Criteria
Approval of final drawing and all the
options Jan Client PM and the client approve
Land preparation, landscape, and
foundation Jan CM PM and CM approval
External work completion and
utilities hookup Apr CM PM and CM approval
Internal and external finish work and
painting May CM PM and CM approval
County clearance and Certificate of
Occupancy May CM County Inspectors and PM
Financial settlement and handover
of home Jun PM Client Design Specifications approval
by PM and Client
Risks.
Project Risks Risk Owner Contingency Plans
County approval and permissions SHC PM None
County property taxes hike Client, SHC Document as contract clause
Traffic congestion Client, County, DMV None
Resources Required.
Funding: the client, underwriters, and SHC
People: SHC project management team, contractors, subcontractors, and skilled labor
Equipment: construction equipment, tools, and machinery
Material: Building materials, appliances, landscaping, shrubs, trees
Stakeholders.
Stakeholder Primary, Other Contingency Plans
Client Primary Overall project cost, time, quality
SHC Primary Overall project cost, time, quality,
success criteria
County Offices Primary Adherence to the county standards
Contractors Other Timely payment of invoices
Suppliers Other Business expansion, profits
Utility Companies Other Adherence to laws, business expansion
Team Operating Principles.
Commitment to project schedule. Project team and contractors will complete their assigned
work as per schedule.
Progress meetings. Construction team meetings scheduled on Mondays at AM every week.
Members should prepare for these meetings with information required for review.
Communication. Regular updates of status, reporting issues, and weekly progress reports.
Lessons Learned.
Team participation in developing project schedule is critical.
Transparent communication is encouraged for resolving issues.
Conflicts must be reported to the construction manager immediately.
County laws and utility standards must not be compromised.
Commitment.
Sponsor DepartmentOrganization Signature
Project Manager DepartmentOrganization Signature
Core Team Members DepartmentOrganization Signature
Suburban homes, once a mediumsized company, is rapidly expanding its business to southern states and
is focused on maintaining its status as the fastest growing construction company in the Midwest region of
the United States. Its significant growth and good reputation for building quality singlefamily homes and
townhomes presents both challenges and opportunities.
Suburban Homes is considering various options to expand its operations while retaining its focus on
managing resources effectively and efficiently to increase profits:
Given the nature of its projects, Suburban Homes is considering either a projectized or matrix
organization structure. However, a functional organization structure has not been ruled out.
With its focus on maintaining highquality in its construction tasks and endproduct home for the
customer as well as quality assurance in implementing project management processes, the
company is actively considering a combination of the DMAIC model with a transitional project
lifecycle approach.
Organization culture plays an important role in sustaining and promoting efficiency. The culture,
in turn, is influenced by the organization structure. Suburban Homes is highly committed to
employee development and functional expertise through training, mentoring, and collaborative
learning.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock